The 60-kilometre section running through Quang Ngai Province is part of the 88-kilometre sub-project linking Quang Ngai and Binh Dinh. The site clearance will affect roughly 2,000 households, including 1,000 that need to be relocated.

Quang Ngai has asked the Ministry of Transport to provide VND4.2 trillion in funding for the North-South Expressway project site clearance.
According to the provincial people’s committee, around VND4.2 trillion needs to be used for site clearance. Of the sum, VND1.4 trillion is for this year.
Quang Ngai has built 23 resettlement areas with a total area of 121 hectares so far. The province will need to spend VND40 billion for relocating 214,000 graves.
The VND20.5 trillion Quang Ngai-Hoai Nhon Expressway sub-project is scheduled to be started in the fourth quarter of this year. It is expected to be put into operation in 2026.