HCM City continues seeking funds for Metro Line 1
The metro line has been built from the official development assistance (ODA) source from the central government and reciprocal capital from the city budget.
According to the plan, the city will be given VND7.5trn (USD320m) from 2016 to 2020. In 2016 and 2017, the city received over VND2.7trn. However, the cost of the project increased last year so the plan had to be readjusted. No funding is allocated to the HCM City's Metro Line 1 project in the state budget investment plan for 2019 by the Ministry of Planning and Investment.
HCM City’s metro lines are facing various issues with procedures, disbursement, and cost overruns. The city had to pay in advance with their own budget multiple times.
Meanwhile, the HCM City Urban Railway Management Board is also seeking VND39bn (USD1.6m) to pay employee wages and bonuses. According to the HMC City Urban Railway Management Board, their employees have only received basic wages since January 31.