Under the Ministry of Transport’s decision, the projects have a total length of 700 kilometres, including the major sections of Ha Tinh-Quang Tri, Quang Ngai-Nha Trang and Can Tho.

The Ministry of Transport has approved an investment of VND147 trillion (USD6.33 billion) for 12 North-South expressway subprojects
The government instructed concerned agencies in February to co-operate with localities to carry out the sub-projects.
The ministry finished the appraisal of the project’s feasible study by late June.
The ministry will complete procedures to start the project before December this year.
Localities have been asked to hand over 70 percent of the land allocated for site clearance before November 20