Site clearance is being implemented on a 5-hectare swamp in Binh Hung Commune for the Binh Chanh Field Hospital.


Over the past week, hundreds of trucks transported construction materials to the site.

Dao Van Chi, director of the hospital, said that around 200 workers divided into three working shifts would work round the clock to hasten site clearance.

The first phase of the work is slated to be put into operation on August 30, with the second work finished by September 30.

Each room will have five sick beds. Heat insulation materials will be used for the roofs.

The project management board arranged workers to clean soil and stones on some sections of Nguyen Van Linh Road scattering from trucks.