Plei Kan Hydropower Project
According to witnesses, people died and were injured because the workers pulled onto each other when falling.
The police and local authorities in Ngoc Hoi District quickly arrived at the scene. The cause of the accident is still being investigated.
On October 17, 2016, Kon Tum People's Committee approved the VND576bn (USD24.6m) Plei Kan Hydropower Plant Project invested by Tan Phat Company in Plei Kan Town, including VND403bn of loans from Agribank. The plant has a design capacity of 17MW.