Located in Cam Nhuong Commune, Cam Xuyen District, the port spans five hectares and is recognised as one of the most modern fishing ports in the region.
Construction of the port began early last year. To date, the project is nearly complete.
The project investor, the Ha Tinh Management Board for Agricultural and Rural Development Investment and Construction Projects, has requested that the contractor complete dredging the waterways before handover and put the project into operation.

According to Nguyen Hong Son, a technical officer from the Ha Tinh Management Board for Agricultural and Rural Development Investment and Construction Projects, the project has been mostly finished.

The port's seafood sorting area spans 2,400 square metres.

The fire prevention and control system has been entirely installed.

The administration building has been finished.


The security camera and lighting system

The 780-metre-long sand-break dyke of the port

The wharf area will require a dredge of 225,000 cubic metres