Saigon River pedestrian bridge set for main span installation this month

The 3,400-tonne main span of HCM City's Saigon River pedestrian bridge is expected to be transported by water and installed on October 21, marking a major construction milestone.

According to the contractor, the span will leave an assembly facility in Vung Tau on October 18 and travel approximately 124 kilometres by water to the construction site in Saigon Ward.

Saigon River pedestrian bridge set for main span installation this month - 1
The nipa palm leaf-shaped main span at a factory in Vung Tau. (Photo: Nutifood)

The structure is scheduled to be lifted onto its completed supports on October 21, connecting the main span with the bridge's approaches.

Designed to resemble a nipa palm leaf, the curved span will provide sufficient clearance for vessels passing beneath the bridge.

Construction began on March 29, 2025, with an investment of nearly VND 1 trillion (USD 38 million).

Saigon River pedestrian bridge set for main span installation this month - 2
The design of the pedestrian bridge over Saigon River

The pedestrian bridge will measure 720 metres in length and between six and 11 metres in width. Its main river-crossing span will extend 187 metres, with a navigation clearance of 80 metres horizontally and 10 metres vertically.

The approach structures and supports required for installing the main span have largely been completed.

Source: Dtinews
More news
Imported fruit gets cheaper in Vietnam

Imported fruit gets cheaper in Vietnam

From Envy apples and shine muscat grapes to red-fleshed peaches, imported fruit is becoming significantly cheaper in Vietnam as supplies increase and...
Loading...