The expressway is designed to have four lanes and run 60 kilometres
According to the ministry's plan, the first phase of the project will have an estimated investment of over VND8.36 trillion (USD364 million), using the public-private partnership model. The investment will include VND7 trillion mobilised from private sectors and VND1.3 trillion from the state budget.
The expressway is designed to have four lanes and run 60 kilometres, starting at the intersection with National Highway 1 and ending at a connecting point with the Tan Phu - Bao Loc expressway project.
The Transport Ministry proposed construction of the project to be started in 2023 and be completed in 2025.