Defence ministry urged to transfer land for Tan Son Nhat Airport expansion
Tan Son Nhat Terminal 3 project was approved by the prime minister in 2020. The new terminal will have the capacity to serve 20 million passengers a year, raising Tan Son Nhat Airport's capacity to 50 million passengers a year.
Lai Xuan Thanh, chairman of the Board of Airports Corporation of Vietnam, said the new terminal would cost VND11trn (USD474m). The investor is completing all required procedures to start construction this October. The project is expected to be completed in two years. In order to meet the schedule, the Ministry of Defence must transfer the land this second quarter.
A road project leading to the new terminal and connecting Tran Quoc Hoan and Cong Hoa streets will also be started at the same time. The project requires 11.8ha of land.
HCM City authorities will ask the Ministry of Defence to convert 11.8ha of land into public land for traffic infrastructure.