DTiNews
  1. VIETNAM TODAY

Hanoi streets face overnight barriers during lighting works

Hanoi authorities will install temporary nighttime barriers on several major roads from May 30 to August 30 to facilitate a project upgrading the city’s lighting system.

According to the municipal Department of Construction, the works will be carried out along the Lang Ha-Le Van Luong and Hoang Minh Giam-Nguyen Chanh-Tran Duy Hung corridors.

Under the traffic plan, contractors will erect mobile barriers about 3.5 metres wide along left-side lanes near median strips and flyover sections to allow lifting equipment and construction vehicles to operate.

On the Lang Ha-Le Van Luong route, construction will be carried out in two phases covering both traffic directions beneath the Lang Ha-Le Van Luong overpass.

A similar two-phase arrangement will apply to the Hoang Minh Giam-Nguyen Chanh route, where decorative lighting systems will be upgraded along sections near the Hoang Minh Giam-Nguyen Chanh-Tran Duy Hung flyover.

Authorities said construction and traffic restrictions would only take place overnight from 10 pm to 5 am in an effort to minimise disruption during peak traffic hours.

Contractors have also been instructed to remove all construction vehicles and equipment from the roads before 5 a.m. each day to help reduce congestion risks.