Long Thanh Airport builders add night shifts to meet deadline

Contractors at Long Thanh International Airport are increasing night-time construction and recruiting more workers as they race to complete Vietnam's largest aviation project on schedule.

The Airports Corporation of Vietnam (ACV) reported progress on the Long Thanh International Airport project to construction minister Tran Hong Minh during an inspection visit to the site in Dong Nai on June 13.

Long Thanh Airport builders add night shifts to meet deadline - 1

Construction Minister Tran Hong Minh inspects progress at Long Thanh International Airport on June 13 (Photo: Hoang Binh).

The inspection team reviewed several key components of the project, including transport links, internal airport roads, the passenger terminal and aircraft apron areas, to assess progress and address obstacles ahead of the airport's planned opening later this year.

According to ACV, the project has now surpassed 76 per cent completion. Workforce shortages have gradually eased, with the project currently lacking fewer than 2,000 workers compared with planned staffing levels.

Contractors have organised multiple work shifts and round-the-clock construction schedules to keep the project on track.

Long Thanh Airport builders add night shifts to meet deadline - 2

The current state of Long Thanh Airport's passenger terminal (Photo: Hoang Binh).

Nguyen Duc Hung, acting chief executive of ACV, said some finishing works at the passenger terminal remained short of workers, particularly skilled technical labour. Other sections of the project are also facing shortages of vehicle operators.

ACV has instructed contractors to deploy sufficient staffing levels, and where possible exceed requirements, to maintain day-and-night construction and minimise weather-related disruptions during the peak rainy season.

The Long Thanh construction site currently employs an average of more than 6,800 workers directly on site, up 6.51 per cent from the end of May. ACV is pressing contractors to increase the workforce to nearly 9,000 direct workers, supported by additional indirect staff, in an effort to accelerate progress.

Long Thanh Airport builders add night shifts to meet deadline - 3

An automation engineer works at the Long Thanh Airport passenger terminal construction site (Photo: Hoang Binh).

During the inspection, Tran Hong Minh stressed the importance of meeting the project's completion target. He instructed relevant agencies to review construction volumes and payment documentation while ensuring engineers and workers receive adequate support as they continue working around the clock.

The Long Thanh International Airport project was approved by the National Assembly in 2015 with a total investment of more than USD 16 billion. The airport is being developed on nearly 5,000 hectares in Dong Nai Province.

The first test flight arrived at the airport in late 2025, and the facility is expected to begin commercial operations by the end of this year.