A VND12trn (USD516m) highway connecting Bac Giang and Lang Son Province is being completed and will soon be put into operation.
Some photos of the highway:
The build-operate-transfer project was started in July 2015 and is nearly 170km long. It is 25 metres wide with four lanes and a speed limit of 100km/h
Bac Giang-Lang Son Highway runs in parallel with the National Highway 1
The project has been completed three months earlier than the deadline of December 2019
Final works are being completed
Foreign experts and local employees are working hard in the final days of the project