A project to upgrade Xuyen Tam Canal in HCM City was approved in 2002, but to date, it has remained on paper, resulting in serious pollution.

A project to upgrade Xuyen Tam Canal in HCM City was approved in 2002, but to date, it has remained on paper, resulting in serious pollution.

HCM City canal awaits two-decade late upgrade - 1

Xuyen Tam Canal connects Nhieu Loc-Thi Nghe Canal in Binh Thanh District and Vam Thuan River in Go Vap District.

HCM City canal awaits two-decade late upgrade - 2

Xuyen Tam Canal is 8.2 kilometres long, consisting of a 6.21-km main section and three branches with a total length of 1.9 kilometres.


HCM City canal awaits two-decade late upgrade - 3

Temporary houses run along the canal. Many households have been living by the canal for dozens of years.


HCM City canal awaits two-decade late upgrade - 4

People who live by the canal discharge rubbish and wastewater directly into the canal, worsening the canal’s pollution. It also has not been dredged for many years.


HCM City canal awaits two-decade late upgrade - 5

A local resident said that her family has to face a bad smell from the canal every day. The pollution is worsening.


HCM City canal awaits two-decade late upgrade - 6

The canal bed is full of litter after the flood tides retreat.


HCM City canal awaits two-decade late upgrade - 7

The canal has also narrowed because of houses encroaching on the waterway.

HCM City canal awaits two-decade late upgrade - 8

Piles of rubbish by the canal


HCM City canal awaits two-decade late upgrade - 9

Some sections of the canal are less polluted.

Chairman of HCM City’s People Committee, Phan Van Mai, has agreed in principle to form a task force to study and prepare the canal project.

Last year, the city sought government approval to invest VND9.35 trillion into the canal’s upgrading.
Source: dtinews.vn