Noi Bai airport taxiway resumes operation after upgrade

Noi Bai International Airport’s new taxiway has been put into service today, November 6, after being upgraded.

Noi Bai International Airport’s new taxiway has been put into service today, November 6, after being upgraded.

According to the Civil Aviation Administration of Vietnam (CAAV), S2 taxiway is part of a project to upgrade Noi Bai International Airport.

The taxiway’s safety check was conducted by the CAAV on Thursday.

Noi Bai airport taxiway resumes operation after upgrade - 1
 

The project to upgrade Noi Bai International Airport is underway


The Noi Bai International Airport upgrade project cost VND2.03 trillion (USD86.95 million), focusing on the repair and upgrade of runways 1A and 1B, taxiways as well as other supporting facilities.

The first phase of the project is scheduled to be finished before December 31, meanwhile the second is slated for completion a year later.

Deputy Prime Minister Truong Hoa Binh recently inspected progress of the upgrading projects at Noi Bai and Tan Son Nhat international airports.

Deputy Prime Minister Le Anh Tuan said that the project’s pace was ensured, but he asked the government to allocate an additional VND230 billion (USD10 million) for the project at Noi Bai International Airport. Tan Son Nhat International Airport would also receive an additional VND300 billion (USD13 million) for its upgrades.
Content link: https://dtinews.dantri.com.vn/vietnam-today/noi-bai-airport-taxiway-resumes-operation-after-upgrade-20201106114534290.htm