Violations valued at over VND300bn (USD13.63m) have been uncovered in the construction of the Ha Long-Van Don Expressway, Quang Ninh Province.
Violations uncovered in the construction of the Ha Long-Van Don Expressway
Three packages to relocate the electric lines of 35kV, 6kV and 0.4kV and the water mains of the Ha Long-Mong Duong section worth VND300bn have the most serious violations.
According to the inspectors of Quang Ninh Province, authorities of Cam Pha City had committed wrongdoings when allocating VND180bn (USD8.18m) package to Thanh Cong Equipment and Engineer JSC, VND78bn package to Tham Gia JSC and VND16bn package to Nam Thang Construction Company.
Contractor Thanh Cong Equipment and Engineer JSC is two months behind schedule in completing the VND87bn package. The company even changed the measurements and foundations.
Contractors Tham Gia JSC, Nam Thang Construction Company, Quang Ninh Clean Water JSC have violated regulations through corner-cutting, using wrong designs and low-quality materials.
Those companies are not specialised in electricity and clean water systems.
The inspectors asked Cam Pha City authorities to review the case and punish related individuals. Supervisors and consultants must take responsibilities.
Bui Dang Trieu, Deputy Office manager of Cam Pha City said they were considering punishments for Hoang Thi Ngoc Hoa, head of the Finance and Planning Office, Hoang Cong Bon, head of the Natural Resources Office and Nguyen Cong Tho, head of the Centre for Land Fund Development.